The Bond Program picked up momentum in 2005 by building on the successful administration of the program in 2004. Some of the 2005 highlights include:

  • More than $306 million was spent on various contracts and purchases, which means that about 74 percent of the total projected expenditures have been completed.
  • About $425 million was spent on construction.
  • All but two of the planned 22 sites for new construction have been selected and acquired.
  • The use of minority- and women-owned businesses at the prime and subcontracting levels increased by 7 percent to 41 percent.
  • Design work was completed on all but 17 of the 226 renovations and additions planned for existing schools and facilities.
  • Construction work at 77 schools was completed, and work at another 98 schools was substantially complete.

For more information, consult the complete 2006 Bond Program Annual Report.