• 2120 W. Jefferson Blvd. | Dallas, TX 75208 | www.dallasisd.org/Sunset

    Sunset High School is set for a $46 million makeover to the historic 1925 Oak Cliff campus.  The additions and renovations will strengthen the school’s unparalleled commitment to education, tradition and strong parent and community support.  The project will focus on four areas: refresh, rejuvenate and maximize existing areas, security enhancements, improve a sense of place and provide new and enhanced fine arts and athletic facilities. The scope of work will refresh and unify the existing building, providing a much-needed facelift while retaining the building's historic character.  The reimagined Sunset includes: 

    • Restoration of the historic building facade
    • Fine Arts addition including choir and black box theater
    • 1,000-seat competition gym
    • New secure main entrance
    • New storm shelter
    • Expanded and renovated administration area
    • Roof and window replacements
    • Renovated athletics area
    • Refresh and unify the existing building
    • Classroom consolidation onto the main campus
    • New parking lot with pick-up/drop-off improvements
    • Existing classroom renovations
    • Transforming annex classrooms to administrative areas

    Take a sneak peek at the new Sunset High School

     

  • Key Information

    Total Budget: $46,279,081.51
    Architect: Corgan
    Contractor: TBD
    Program Manager: Dallas ISD
    Project Manager:
    Katy Lenihan, RA 
    klenihan@dallasisd.org

Project Timeline

  • 1 Planning
    Completed
    Checkmark-Completed
    2 Design
    Completed
    Checkmark-Completed
    3 Construction
    Addition - 9% complete
    Phase 1 Renovations - 30% complete
     Work In Progress
    4 Ribbon-Cutting  
    5 Target Opening
    Scheduled Fall 2023
     
    6 Project Close-Out
    Scheduled 2023
     

     

Related News