• 4001 Walnut Hill Ln | Dallas, TX 75229 | www.dallasisd.org/tj

     

    Thomas Jefferson High School is receiving an $82M renovation and addition.  Following the October 20, 2019 tornados that devastated the campus, much of the existing TJ campus will remain and receive needed renovations. The cafeteria/kitchen, weight room/dance studio, and culinary/ROTC areas will be demolished. Additions will be added to the existing building and the addition under construction will be completed. The full scope of the project is below:

    • Complete previous 13 classroom addition
    • New competition Gymnasium, weight room, and overall athletic improvements
    • New Kitchen/Cafeteria
    • New ROTC area
    • New Engineering, Culinary Arts, and Computer Science Labs
    • New library and administration areas
    • Renovation of existing educational spaces and Visual & Performing Arts spaces
    • Mechanical, electrical, and plumbing improvements throughout the campus
  • Key Information

    Total Budget: $82,000,000
    Architect: VAI Architects
    Contractor: Beck
    Program Manager: Dikita\\Vanir JV
    Project Manager:
    Kevin Simon
    ksimon@dallasisd.org

    Disclaimer:  Funding for this project comes from multiple sources including Bond 2015.

     

Project Timeline

  • 2 Planning
    Completed
    Checkmark-Completed
    2 Design
    74% completed
    Work In Progress
    4 Construction
    1.5% completed
     Work In Progress
    6 Ribbon-Cutting  
    5 Target Opening
    August 2022
     
    6 Project Close-Out
    Scheduled 2022
     

     

Related News

Other Resources