Bryan Adams High School
-
2101 Millmar Dr. | Dallas, TX 75228| www.dallasisd.org/bryanadams
Bryan Adams High School is receiving a $69.28M addition and renovations to the existing campus to include:
- New administration offices
- New secured main entry
- New two-level classroom addition
- New fine arts addition
- New competition gym and athletics addition/storm shelter
- New exterior monument sign
- New concrete fire lanes
- Auditorium upgrades
- Upgrades to the existing outdoor plaza
- Renovations to existing classrooms and corridors and new interior signage
- Renovations to the existing building
- Renovations to Library and Media center
-
Key Information
Total Budget: $69,279,002.50
Architect: BRW Architects
Contractor: Sedalco Construction
Program Manager: Dallas ISD Construction Services
Project Manager:
Qamarul Haque
QHAQUE@dallasisd.org
Project Timeline
-
Planning
CompletedDesign
CompletedConstruction
47% complete
Ribbon-Cutting Target Opening
Scheduled August 2022Project Close-Out
Scheduled 2022
Related News
Other Resources
-
Landscape concept full growth plan
2021-0306 Bryan Adams_Landscape Concept Full Growth_P.pdf 524.32 KB (Last Modified on March 9, 2021) -
Stone Retaining Wall Example
2021-0305 Bryan Adams HS_Retaining Wall Stone Example_P.pdf 106.41 KB (Last Modified on March 9, 2021)