- Bond 2015
- Bond 2015 Progress
- West Dallas STEM School at Pinkston
Bond 2015 Progress
Page Navigation
-
Bond 2015 Progress
- Barbara Jordan Elementary School
- Casa View Elementary School
- Charles A. Gill Elementary
- Dr. Martin Luther King , Jr. Arts Academy
- H. I. Holland Elementary School
- James Madison High School
- Rosemont Upper School
- School for the Talented and Gifted Pleasant Grove
- Sunset High School
- West Dallas STEM School at Pinkston
West Dallas STEM School at Pinkston
-
2200 Dennison Street | Dallas, TX 75212
The $35 million project will transform the existing L. G. Pinkston High School Campus into the new PK- 8th grade West Dallas STEM School at Pinkston. The scope of work will include:
- New main entrance with secure vestibule
- Renovations to administration and communication/specialized counseling suits
- New STEM labs
- Renovations to athletics area
- Upgraded middle school learning courtyards
- New STEM courtyards
- Renovated classrooms
- Renovation to the existing library
- Reconfiguring existing classrooms and learning spaces
-
Key Information
Total Budget: $33,928,225.95
Architect: VAI
Contractor: Reeder General Contractor, Inc.
Program Manager: AECOM
Project Manager: Edgar Hinojosa
Project Timeline
-
Planning
CompletedDesign
CompletedConstruction
Phase 1 - 100% Completed (STEM)
Phase 2 - 90% Completed (Roofing & Windows)
Phase 3 - 30% Completed (Resource Center)
Phase 4 - Scheduled Fall 2024 (Renovations to the entire campus.)Target Opening
Fall 2024Project Close-Out
Fall 2024