• 2200 Dennison Street | Dallas, TX 75212

    The $35 million project will transform the existing L. G. Pinkston High School Campus into the new PK- 8th grade West Dallas STEM School at Pinkston. The scope of work will include:

    • New main entrance with secure vestibule
    • Renovations to administration and communication/specialized counseling suits
    • New STEM labs
    • Renovations to athletics area
    • Upgraded middle school learning courtyards
    • New STEM courtyards
    • Renovated classrooms
    • Renovation to the existing library
    • Reconfiguring existing classrooms and learning spaces

     

  • Key Information

    Total Budget: $33,928,225.95
    Architect: VAI
    Contractor: Reeder General Contractor, Inc.
    Program Manager: AECOM
    Project Manager: Edgar Hinojosa

Project Timeline

  • planning Planning
    Completed
    check
    design Design
    Completed
     
    construction

    Construction
    Phase 1 - 100% Completed (STEM)
    Phase 2 - 90% Completed (Roofing & Windows)
    Phase 3 - 30% Completed (Resource Center)
    Phase 4 - Scheduled Fall 2024 (Renovations to the entire campus.)

    1
    open Target Opening
    Fall 2024
     
    close out Project Close-Out
    Fall 2024
     

     