Nathan Adams Elementary is undergoing a $6.72 million renovation that includes:
Exterior Renovations:
- Replace all exterior windows throughout
- Provide new front entry canopy
- Replace ADA entry ramp
- Replace concrete paving as required
- Replace asphalt play area with concrete
- Add concrete paving to dumpster drive
- Provide enclosure for existing recycling dumpster
- Replace existing marquee sign with new LED sign
- Paint all previously painted exterior surfaces
- Replace exterior and site lighting with LED fixtures
Interior Renovations:
- Provide new secured front entry vestibule
- Provide new reception and principal’s office
- Replace carpet and vinyl composition tiles in areas specified
- Paint all previously painted interior surfaces, including walls and ceiling
- Replace interior lighting throughout with LED fixtures
- Replace fire alarm system
- Replace various mechanical equipment
- Replace various plumbing and mechanical piping
-
Key Information
Total Budget: $6,722,809
Construction Budget: $4,400,00
Architect: T. Howard Architecture
Contractor: Reeder General Contractors
Project Timeline
-
Planning
CompletedDesign
CompletedConstruction
on scheduleRibbon-Cutting Target Opening
Scheduled February 2022Project Close-Out
Scheduled 2022