- Bond 2015
- Mount Auburn Elementary
Completed Projects
Page Navigation
- Completed Projects
- Districtwide Projects
- Alex Sanger Preparatory School
- Ascher Silberstein Elementary
- B. H. Macon Elementary School
- Bryan Adams High School
- C. F. Carr Elementary
- Central Elementary
- Chapel Hill Preparatory
- Charmaine and Robert Price, Sr. Career Institute
- Dan D. Rogers Elementary
- Daniel Webster Elementary School
- David W. Carter High School
- Eddie Bernice Johnson Elementary School
- Edna Rowe Elementary School
- Eduardo Mata Montessori School
- Eladio R. Martinez Learning Center
- Franklin D. Roosevelt High School
- H. S. Thompson Elementary School
- Hillcrest High School
- Jesus Moroles Expressive Arts Vanguard
- Jill Stone Elementary
- John Pershing Elementary
- Justin F. Kimball High School
- L. G. Pinkston High School
- L. O. Donald Elementary School
- Lorenzo De Zavala Elementary School
- Moises Molina High School
- Mount Auburn Elementary
- Nathan Adams Elementary
- Nathaniel Hawthorne Elementary
- New Tech High School at B. F. Darrell
- North Dallas High School
- Prestonwood Montessori at E. D. Walker Middle School
- Robert T. Hill Middle School
- Seagoville High School
- Solar Prep for Girls
- South Oak Cliff High School
- Thomas Jefferson High School
- Tom C. Gooch Elementary
- W. T. White High School
- W. W. Samuell High School
- Walnut Hill PK-8
- William Anderson Elementary
- Woodrow Wilson High School
Mount Auburn Elementary School
-
6012 East Grand Ave., | Dallas, TX 75223 | www.dallasisd.org/mountauburn
Mount Auburn Elementary School is receiving $7,300,316 in renovations to its campus to create a safe, nurturing learning environment. The scope of work includes
-
Exterior Renovations
- Main Entry – Landscaping & Signage
- Clean, Repair & Paint Building Façade
- Replace Select Doors & Transom Windows
- Improved Drainage
- Replace portions of Walks & Drives
- HVAC System Replacement
- Plumbing
- New Exterior Lighting
- Interior Renovations
- Replace Flooring – VCT, Carpet & Tile
- Replace Ceilings & Lighting
- Create New Secure Front Vestibule/Main Office
- Renovate Gym Restroom
- HVAC Systems Replacement
- Paint Walls and Hard Ceilings
- Create Room for Kiln in Art Room
-
-
Key Information
Total Budget: $7,300,316
Architect: Jacobs & Associates
Contractor: SDB Contracting Services, Inc.
Project Timeline
-
Planning
CompletedDesign
CompletedConstruction
CompletedRibbon-Cutting
CompletedOpening
March 2022Project Close-Out
Completed